SA – Emergency Plan advises it is a requirement of AS 3745 – 2010 ‘Planning for emergencies in facilities’ that emergency response procedures be tested within the first 12 months once a facility’s emergency planning committee has deemed them satisfactory and workable and the facility’s emergency control organisation has been trained. AS 3745 also requires the first emergency response exercise be an evacuation exercise and thereafter, a program of site-specific emergency response exercises including evacuation exercises be developed for the facility…(more)