QLD – HENDRY building certifiers advise that to expedite the construction of a building an applicant can apply to the building certifier for a building approval for a stage of building workThis type of building approval documentation (full compliance with the building regulations (Building Code of Australia) for a full building approval is lodged with the building certifier.

The Building Act 1975 in section 70 states:

Engineering drawings

qld_bldg_act_1975(1)   This section applies if –                                                                                                                                                                                                                                       a)      supporting documents for a building development application are in the form of engineer’s drawings or other engineering details; and                                                                                                                                                                                             b)      the drawings or details were not included with the application; and                                                                                                                                                               c)      the application is approved                                                                                                                                                                                                                               (2)   Work on any footings for the building work must not start until the drawings and details for the footings have been approved by the building certifier.

(3)   A stage of the building work must not be started until the drawings and details for the stage have been approved by the building certifier.

Certifiers may also be restricted on issuing a staged approval if other authority approval are required or there is not enough design documentation to clearly delineate each stage.

IDAS form 2 Building Work

An applicant may request a staged building approval by identifying the stage(s) required on the application formBuilding work requiring assessment against the Building Act 1975 – IDAS form 2.

Building Legislation Table

Refer to our Building Legislation table for further information on the building control process including the Development Permit and Certificate of Classification.

Further Advice

For building surveying advice consultancy advice please contact our closest HENDRY office by clicking here.